|
| FERC ordering a settlement judge on the Kammer-Juniata formula rates is the second such proceeding on a 765-kV PJM project in one week. Why the commission is moving this way in quick succession is not stated in the source. For developers financing PJM transmission on a formula-rate model, the settlement process adds time and introduces uncertainty on the cost-recovery side of the capital stack. |
| AVAIO's $6B campus drops a 150MW phase-one load into Entergy Arkansas territory in MISO South, with a build-out path to 1GW across 15 buildings. The real signal is the friction: Wrightsville's pushback and Pulaski County's own data center moratorium put Arkansas on the same opposition curve as Virginia and Pennsylvania, where entitlement, not power, is the binding constraint. Phase one already has its permits, but anyone underwriting the gigawatt expansion should watch whether the county moratorium hardens before later phases file. For developers hunting shovel-ready MISO South land, local zoning is now the gating item. |
| The Lazard report confirms renewables remain the cheapest new US generation source even as costs rose across all technologies, while rising demand has driven a sharp increase in new-build gas. For data center developers pricing long-term power, the gap between gas and renewable new-build costs now matters more, not less. Whether current ITC and PTC structures remain accessible at scale depends on legislative developments that are not yet settled. |
| The Lazard data shows US utility-scale BESS costs have risen, reversing prior declines. Lazard attributes the increase to import tariffs and FEOC restrictions that cut off low-cost Chinese cell supply. Developers who underwrote storage into co-location or campus power plans at prior benchmarks need to rerun the economics. FEOC compliance documentation is now a first-order underwriting question, not a closing checklist item. |
EL26-67-000 · PJM · cost allocation · 3 filings FERC initiates Section 206 proceeding against PJM, all commissioners concurring separately |
ER26-1323-002 · SPP · large load SPP compliance filing for conditional high-impact large load service tariff provisions Filed 2026-07-06 20260706-5174 › |
ER26-2698-000 · NYISO · queue reform NYISO supplemental filing on interconnection process improvements affecting queue procedures Filed 2026-07-08 20260708-5191 › |
EL25-49-002 · PJM · large load FERC issues rehearing/clarification order on PJM proceeding, likely large-load or cost policy matter. Filed 2026-06-18 20260618-3103 › |
ER26-2514-000 · SPP · queue reform FERC accepts SPP generator interconnection procedure revisions to Attachment V tariff. Filed 2026-06-29 20260629-3054 › |
ER26-2771-000 · PJM · queue reform FERC denied Chestnut Run Energy LLC's waiver request in PJM (ER26-2771), a process-integrity ruling on interconnection queue timing. Filed 2026-07-02 20260702-3059 › |
EL26-68-000 · n/a · large load Data Center Coalition intervenes, signaling major data center power policy proceeding. Filed 2026-07-09 20260709-5248 › |
EL26-69-000 · n/a · large load Data Center Coalition intervenes, signaling large-load policy dispute at FERC. Filed 2026-07-09 20260709-5275 › |