| MISO holding its zero-injection generation agreement design largely intact after a month's delay tells you the RTO is committed to the framework despite stakeholder pushback. Zero-injection agreements let generation sited to serve a co-located load connect without exporting to the grid, which is exactly the structure behind-the-meter data center campuses want. The stakeholder apprehension is about cost and precedent, and the delay bought time, not concessions. For anyone structuring a load-plus-generation project in MISO, this is the interconnection path to watch. |
| Senator Heinrich's Grid Connection and Congestion Management Act (S. 5008), introduced July 16 as part of his Grid for Growth initiative, would require grid operators to offer fast-track connect-and-manage interconnection, and if enacted it would be the most consequential federal intervention in the queue crisis to date. Connect and manage lets generators interconnect faster by accepting curtailment when the grid needs it rather than waiting for every network upgrade to be built and paid for, which is why ERCOT's queue moves faster than PJM's or MISO's. The politics are steep, and federal preemption of RTO interconnection design will draw heavy opposition, so treat this as a directional signal rather than an imminent rule. But it names the right problem, and a legislative proposal carries more weight than another stakeholder complaint. |
EL26-67-000 · PJM · cost allocation · 3 filings FERC initiates Section 206 proceeding against PJM, all commissioners concurring separately |
ER26-1323-002 · SPP · large load SPP compliance filing for conditional high-impact large load service tariff provisions Filed 2026-07-06 20260706-5174 › |
ER26-2698-000 · NYISO · queue reform NYISO supplemental filing on interconnection process improvements affecting queue procedures Filed 2026-07-08 20260708-5191 › |
RM21-17-000 · MISO · cost allocation · 3 filings FERC extends time on major MISO regional transmission planning and cost allocation rulemaking. |
EL25-49-002 · PJM · large load FERC issues rehearing/clarification order on PJM proceeding, likely large-load or cost policy matter. Filed 2026-06-18 20260618-3103 › |
ER26-2514-000 · SPP · queue reform FERC accepts SPP generator interconnection procedure revisions to Attachment V tariff. Filed 2026-06-29 20260629-3054 › |
ER26-2771-000 · PJM · queue reform FERC denied Chestnut Run Energy LLC's waiver request in PJM (ER26-2771), a process-integrity ruling on interconnection queue timing. Filed 2026-07-02 20260702-3059 › |
EL26-68-000 · n/a · large load Data Center Coalition intervenes, signaling major data center power policy proceeding. Filed 2026-07-09 20260709-5248 › |